Finally: Commissioning of the Salzburg line
After an approval period of 77 months and a construction period of five years, the commissioning of the new pipeline started these days.
2/4/2025
The new high-capacity Salzburg line with an investment volume of around one billion euros is finally going into operation - in stages.In what Austrian Power Grid calls "the most important electricity infrastructure project in Austria", the first of two 380 kV systems between the Kaprun and Pongau (St. Johann im Pongau) substations has now been…